Drain Dismantling & Rectification & New Drain Construction

February 17, 2019

Client: Toyota Kirloskar Motors (TKM)

Nature of Work: Dismantling & Rectification Works

 

Existing drain was rectified by dismantling the existing damaged stone pitching, compacting the surface & relaying with fresh stone pitching. 

 

Consequently new drainage system had been proposed which consisted of about 2000 Cum of excavation, 1500 Sqm of Stone Pitching, about 100 Cum of concrete, so on and so forth. 

 

 

 