Drain Dismantling & Rectification & New Drain Construction
Project Details :
Project Year: 2018
Client: Toyota Kirloskar Motor (TKM)
Nature of Work: Dismantling & Rectification Works.
Rectification of damaged drains to improve water flow.
Existing drain was rectified by dismantling the existing damaged stone pitching, compacting the surface & relaying with fresh stone pitching.
New drains were constructed with improved gradient, Consequently new drainage system had been proposed which consisted of about 2000 Cum of excavation, 1500 Sqm of Stone Pitching, about 100 Cum of concrete, so on and so forth.
Drainage efficiency and hygiene were restored.
Project Gallery



